Gabion Fill Wall

Gabion wall for fill situations.

Typical Cross Section

Parameters

bSGSuperSet to one if the sub-grade has crown or superelevation.
SG_VOffsetWall vertical offset from profile attachment point.
WallOffsetXHorizontal offset from centerline.
BlockWidthWidth of a block (as seen in the cross section).
BlockHeightHeight of a block.
BlockOffsetHorizontal offset from inside of block to inside of block above. This value should be less than BlockWidth.
WallRowFactorPercent of the bottom face of the bottom block which can be above ground.
WallBaseOffsetHorizontal offset at the bottom of the wall.
WallBaseSlopeWall base offsett slope