Slope XIX Rock Fill Slope
Updated July 27, 2022
This article applies to:
- RoadEng Civil
- RoadEng Forestry
Slope XIX Rock Fill Slope
Stacked rock fill on keyed in at toe. Add before other components.
Typical Cross Section

Parameters
| RoadSGwidth | Road subgrade width. | |
| RockFillSlope | Fill slope of rock. | |
| ExtraWidthAtToe | Extra Horizontal Width For Rock Fill at Toe | |
| RockFillThickness | Thickness Of Rock Fill Slope | |
| KeyInDepth | Depth to key in material at toe. | |
| KeyInCutSlopeOut | Outside excavation slope to key in rock fill. | |
| SlopeOfExcFloor | Slope of excavation floor. | |
| KeyInCutSlopeIn | Keyed in cutslope inside. |