Stacked rock fill on keyed in at toe. Add before other components.
Typical Cross Section
Parameters
RoadSGwidth | Road subgrade width. | |
RockFillSlope | Fill slope of rock. | |
ExtraWidthAtToe | Extra Horizontal Width For Rock Fill at Toe | |
RockFillThickness | Thickness Of Rock Fill Slope | |
KeyInDepth | Depth to key in material at toe. | |
KeyInCutSlopeOut | Outside excavation slope to key in rock fill. | |
SlopeOfExcFloor | Slope of excavation floor. | |